
Orlando, Florida
Engineer:
KCG
Contractor:
Phillips and Jordan
Installation:
Summer 2020
Technical Description:
74,439' of 66", 42" and 25" Aluminized Steel Type 2
Due to the project's vast scale (759,000 cubic feet in stormwater storage), stormwater needed to be stored underground to allow the land savings necessary to develop the project on the scale required. KCG Engineering had developed an initial design for the system. Contech worked with KCG and the winning bidder, Phillips and Jordan, to complete the design to ensure it could fit within the challenging site constraints, be permitted, and fall within budget.
Contech was instrumental in solving several design challenges. These included allowing extra cover over electrical conduits, avoiding areas dedicated to high-pressure force mains, and accommodating utility conflicts, tree islands, and light pole foundations.
A key component of Contech's corrugated metal pipe (CMP) solution was its variable diameter design strategy. This strategy allows engineers to select from 120 different pipe sizes to maximize vertical storage space and minimize stone bedding and cover. Three different sizes of CMP were used on this project: 66-inch, 42-inch, and 28-inch. This design saved 19,484 cubic yards of stone compared to a plastic solution, resulting in 2,000 fewer truck deliveries and over $500,000 in stone cost savings.
Given the site's size, multiple basins were constructed on the east and west sides of the development. The east portion of the site included nine basins constructed from 16,986' of 66" diameter pipe. The west portion included twenty basins constructed from 20,863' of 28" diameter pipe and 36,590' of 42" diameter pipe.
Although the detention systems were installed early in the project, the buildings and parking lots are being built in phases. To eliminate the possibility of sediment entering the storage systems during construction, Contech designed temporary baffle walls into the system. These baffle walls will keep sediment-laden runoff from entering the system before site stabilization and were designed to be easily removed later to bring the system fully online upon project completion.
Given the size of the project, managing logistics was essential in enabling the contractor to meet their production goals and ensure the project came in on budget. For this project, Contech's MOBILE PIPE® mill was used to produce the 66-inch pipe on-site. This reduced transportation costs, the number of trucks entering and leaving the busy site, and staging issues. It also allowed Contech to produce longer pipe lengths (50' vs. the traditional 40'), allowing the contractor to reach their installation goal of 2,700 feet of pipe per day.
Technical Description:
74,439' of 66", 42" and 25" Aluminized Steel Type 2
800-338-1122 | www.ContechES.com
© 2025 Contech Engineered Solutions LLC, a QUIKRETE Company